First Main Line Pump Installed for EWPL Project

Recently, pump B of Aramcos Upgrade Crude Oil Delivery System (EWPL Project) PS2 was lifted and set in position, marking a major milestone of the main line pump installation activities. The first pump arrived at Dammam port on December 12, 2024, and in order to complete the expected control point, the project team sped up efforts in customs clearance, transportation, request for quality inspection and other work in an orderly manner. Thanks to meticulous planning by the project team, it took only 90 minutes to complete laydown yard pickup, field unpacking, lifting and setting on the morning of December 25, 2024. This achievement was highly recognized by Aramco's operation, PMT and PID teams.

The successful lifting and setting of the first main line pump lays the groundwork for subsequent pipe erection and testing work, amassing insightful experience for the setting of the remaining three pumps.