Heavy Lifting Work Completed for Jinling Huntsman Project

On  May 22, with the lifting operation safely performed for the last piece of  equipment, R0570-A, for Jinling Hunsman Project, all the heavy work for the  project has been successfully completed.

For  Jinling Huntsman Project, over more than a year since the start of lifting for  the first peroxidation reactor on February 12, 20414, till the completion on May  22, totally 110 sets (times) of rotating equipment, static equipment and  structural steel modules have been lifted, with a total lifted weight of 9,250  tons. The heaviest and biggest equipment is the peroxidation reactor, which  measures 9m in diameter and 700 tons in weight. The tallest equipment lifted is  77m in height.

For  this project, the project management team successfully lifted a pre-assembled  frame that sets the record in China for lifting of the biggest and heaviest  pre-assembled modular structural steel frame.