Successful Intermediate Handover Achieved for Flue Gas DeSOx and DeNOx Project for 3MMT/a FCCU

On  November 19, the flue  gas DeSOx and DeNOx project undertaken by SNEI for the 3MMT/a FCCU achieved  successful intermediate handover.

During  the construction phase, the PMT has overcome multiple adverse factors like  materials, weather and design variations before first achieving the intermediate  handover of the waste heat boiler and DeNOx sections by the end of June this  year, which have been successfully put into operation.

The  project involves multiple disciplines including the existing boiler demolition,  structural steel, static equipment, mechanical equipment, process piping,  electrical, telecommunication, instrumentation, painting, insulation, and heavy  lifting.

The  PMT made reasonable arrangement and coordination by 1) strengthening early  preparations by each discipline with collaboration between the disciplines; 2)  utilizing a Level 4 schedule to manage the plans and targets during the process,  coordinating the work in parallel, as well as safety, quality and housekeeping  on site; 3) strengthening site organization, to address various issues which may  affect project schedule in a timely manner,  and also switching from step-wise work to work in parallel, multi-layer work to  layer-wise work; 4) adjusting the overall construction schedule according to the  actual project progress, and then breaking down the overall construction  schedule, preparing detailed work plan for the critical path, concentrating  efforts on one after another, so as to ensure smooth completion of the project,  and make contribution to SINOPECs  "Blue Sky and Clean Water" Project.

信息来源: 
2022-04-19