The 300kt/a phosphoric acid plant (EPC) of Inner Mongolia Dadi Yuntian Chemical Co., Ltd. has a schedule encompassing 2 winters. In previous years, air temperature during the middle of November is -6 to 5℃. Per regulations by the local construction authority, concrete work shall be suspended in the mid November.
In order to perform the winter activities, based on the weather conditions of Chifeng, the PMT prepared a complete method statement for construction in winter. A steering group is established for winter construction. Freezing protective materials for the winter are purchased. Detailed technical explanation is made for construction work in winter, which defines job responsibilities for the organization members in winter work. On November 1, concrete pouring for the foundation cap of the reactor is successfully completed. Concrete work for the reactor belongs to winter work for large-area concrete, which should consider detrimental cracking caused by temperature variance due to hydration of cementing material in the large-area concrete and shrinkage, and also need to consider freezing protective measures for concrete construction in winter. In order to ensure construction quality, the PMT assigned dedicated personnel to carry out temperature test and freezing protective covering, and check provision of measures for work in winter every day on site. On Nov. 4, after removing formwork for the reactor, the concrete foundation axial lines are straight, the dimensions are accurate, the edges are perpendicular, the surfaces are flat, smooth, clean and have consistent luster, which meets the standard for as-cast concrete, and received recognition by the owner and supervisor, the successful completion of concrete pouring paved the way for subsequent activities.