The Sea Water Cooling Project is a project undertaken by SNEI E&I Branch on its own. Since kick-off of the project on Sept. 20, the PMT has been arranging the construction activities with a high level of quality, and to match with the civil burying work, which is well accepted by the EPC contractor and owner.
During the cable conduit burying, the E&I construction supervisors carefully studied the technical documents, made proper technical preparations, and held close and smooth communication with civil engineers from the EPC contractor and owner to address a number of design issues, which ensured smooth progress of conduit burying for the flow chamber and valve chamber. So far, cable conduit burying has been completed for 5 flow chambers and valve chambers with high quality, which passed the inspection by quality inspectors of owner on the first try, and various other activities are in smooth progress as well.