On September 16, the air compressor station optimization and revamp installation works undertaken by SNEI Storage Tank Engineering Branch achieved handover with good quality and on schedule for SINOPEC Wuhan Company.
The project overall schedule is 175 days. It is a small project but involves everything. In particular, the project is located inside an existing plant, spotty civil works, welding and erection works for spherical tanks, revamp and expansion for process piping have added difficulties to HSE management for construction inside the tank farm, and the congested area has caused increased amount of overlapping activities going on in parallel. In order to make sure the project is completed in a safe manner with good quality, the PMT adopted the management method of “dedicated person for coordinating construction work, dedicated person for HSE management, and dedicated person for quality supervision”, and successfully completed all construction activities for the project. First-time pass rate for welding of spherical tank is 100%. High-standard intermediate handover was achieved according to Client requirements