The project commenced on Aug. 10, 2013. The contract covers manufacturing & installation of a 3,000m3 cryogenic ethylene storage tank and associated pipelines of rotating/static equipment, steel structure, installation of electrical instruments and anticorrosion & insulation project. Standardized construction, safety, quality, progress and others of Project Dept. satisfied the contract requirements, and the owner & EPC contractor gave full acknowledgement.
On Jul. 13th, 3,000m3 cryogenic ethylene storage tanks & associated projects of Yong’an Pharmaceutical contracted by storage tanks branch was initially charged with liquid ethylene, and ethylene compressor, ammonia cooler screw machine & refrigerating brine pump were started at the same time, so that the operation process was lined up and ethylene was charged successfully to achieve one-off successful startup of the project.