On Jul. 7th, civil construction of the middle residue field of coal storage & transportation project for Zhongtian Hechang officially commenced, and kick-off ceremony was held on site.
The major physical quantities related to work in the middle residue field includes 10,000 m2 heavy load terrace and the surrounding drainage system. Project Dept. organized HR, tools & machines and materials to be delivered on site in a timely manner based on the drawings delivered, and provided induction training to personnel, strictly controlled review of qualification of personnel entering site and arranged work plan in a reasonable manner, so as to ensure that the middle residue field will commence on time.