On May 29, the 1.5MMTPA PTA Plant of Honggang Petrochemical in Lianyungang, undertaken by SNEI, achieved first-time-right commissioning and produced on-spec product. From start of commissioning to production of on-spec product, the plant operation is stable and reliable, which reflects SNEI’s state-of-the-art construction techniques and excellent service quality.
SNEI undertakes two major works, civil and installation, for the 1.5 MMTPA PTA project of Honggang Petrochemical. The project commenced on March 20, 2013, with a very aggressive schedule. Despite such great difficulties, the PMT has made planning well in advance to tackle the schedule challenge by promoting the idea to “improve the conditions from outside and create the conditions from inside”, and proactive communication and coordination were maintained with Owner in order to improve the conditions. Arrangements were made such that prefabrication of process piping and erection of structural steel and equipment commenced basically at the same time. Time was extended for prefabrication of pipes, so as to avoid concentration of labor which may result in lack of labor on site for a short term. In the meantime, based on actual construction need, full-swing programs were initiate, including the “100-day” full-swing program for civil works, and the full-spring program for “Q4 and achievement of intermediate handover date on Dec. 29” for installation works. By implementing the management concept of “getting progress along critical path, and getting resources from non-critical path”, the PMT dynamically adjusted the plan to focus on key and difficult activities. By the end of 2013, main construction work for project was completed, and on Mar. 20, 2014, intermediate handover was achieved for the plant.
In a next move, the PMT will make all-out efforts to complete the last important piece of work for the project, close-out activities for pipe insulation, and assist Owner to maintain stable and safe operation of the plant.