Recently, as per the contractual requirements, SNEI’s Guangzhou Shuangqiao PMT has completed all the works for flue gas DeNOx for the 2x35t/h boilers, and achieved mechanical completion.
The project is one of the four EPS environmental projects undertaken by SNEI, which features a short schedule and simplified organization. From contract signing to mechanical completion, the project only takes as short as 90 days, including engineering, procurement and construction.
Since kick-off of the project, the PMT has overcome difficulties in delayed arrival of drawings, materials and equipment by reasonably organizing the construction activities. So far, erection work for the boiler flue gas DeNOx unit has been completed, and has passed 3C4D’s by Owner. Currently, the site has entered the testing phase. After that, they will carry out pipe purging and cleanness inspection and commissioning. By ensuring safety, the PMT will carry out the operations strictly according to the start-up manual, so as to achieve start-up of the project on the first try.