On Mar. 8, the units in the air compression station and air compression cooling water station in the industrial park of Yantai Wanhua contracted by SNEI was put into operation officially with high standard after two days of interim handover.
This project consists of 6 compressor units, cooling water station and 3 * 650M3 spherical tanks, and SNEI is responsible for all civil works & installation works. Although the project scale isn’t large, during the process of implementation, based on the adjustment and optimization of the whole park, the owner adjusted and modified the design drawings for many times, which increased the difficulties in project organization management and other aspects. Project department adjusted the strategy in a timely manner, made communication with each party, studied and judged correct information, prepared materials in advance, utilized the features (many project units, first and last completion time) to balance the work strength synchronously, strengthened coordination & confirmation procedure in the later period and performed work steadily to achieve interim handover on schedule as per the owner’s final comprehensive network plan, so that the production target (supply of gas to outside users) was achieved 7 days in advance.