SNEI Builds A Community In The Desert

The  owner of the Saudi Aramco Hydrocracking Project undertaken by SNEI is Saudi  National Oil Company Saudi Aramco, and the EPC contractor is Technip. As per  requirements of the contract between the Owner and the EPC Contractor, a camp  area should be built at the project site.

 

In  contrast to the contractual schedule of more than 2 years for the main project,  the schedule for the camp area is only six months, but it is a living facility  that is closely related to the livelihood of more than 1,000 staff on site. To  some extent, it is also a small-sized EPC project. From the early site  investigation and survey, engineering design drawings, all the way to  subcontracting, material procurement, plan development and construction, it is  all organized and performed by the Hydrocracking Project Management Team of SNEI  Saudi Branch Company. For this, leaders both from SNEI and SNEI Saudi Branch  Company and also the project management team pay high attention to the building  of the camp area, expecting to make it ready for occupation within the shortest  time possible.

 

Since  commencement of construction from the end of September 2010, the Project  Management Team faces multiple difficulties including the parallel construction  of the 100,000m2  laydown area and the 700m2 offices, and commencement  of main plant steel structure, mechanical and piping work one after another. By  overcoming difficulties like the shortage of manpower and material supply, and  unfamiliarity of the contract specifications, and also by refined engineering  design and planning, strengthening material procurement and coordination, and  scientific organization of construction activities, the Project Management Team  eventually managed to finish the construction of the camp area which measures  about 40,000m2 by the end of May this  year, with high quality. On June 1, the camp area passed the joint inspection  and acceptance by the Owner and EPC Contractor. On June 3, the camp area has  welcomed in the first batch of site staff. Till now, more than 150 persons have  moved in, and other people are moving in by batch.

 

The  camp area involves many different types of buildings, including 103 barracks, 8  toilets, and canteen, refrigeration room, storage room, guard room, shop, clinic  and administration office, etc. Entertainment facilities include activity room,  badminton field and basketball field, etc. The camp area is also provided with a  car park (shed), surrounding flower bed and a signal reception tower. For so  many buildings and associated systems, the designers of the Project Management  Team carefully studied the specifications, and provided excellent design to  achieve a proper arrangement with a pleasant appearance and in accordance with  the safety and functional requirements. Final acceptance by the Owner also shows  that the design is appropriate, which has earned recognition and commendation by  the Owner, making it a splendid masterpiece within the camp area of the  Owner.

 

On  May 20, 2011, all systems in the camp area were finished and ready for  acceptance. On May 21, the Project Management Team submitted the application for  acceptance. On May 22, the Owner, the EPC Contractor and Project Management Team  conducted a joint acceptance of the camp area. Inspection was conducted for each  functional area and system of the camp area. Many problems were identified  during the inspection. The Project Management Team arranged rectification for  several times. After finishing the correction, the Owner and the EPC Contractor  are informed of the inspection. Back and forth, totally more than 6 inspections  were conducted. It should be mentioned that the Owner specifically required the  addition of smoke detection systems in each room and the canteen in the camp  area, with each camera connected to a network system installed in the guard room  and monitored by a dedicated person. In addition, the Owner also raised very  critical requirement on the fire fighting system. The Project Management Team  added 10 fire hoses (boxes), 4x10kg dry powder fire extinguishers, and after  eliminating a number of punchlist items, the camp area eventually started to  welcome the first batch of occupants on June 3.

 

Now,  main hardware like the barracks, canteen, road and office area, and the  associates facilities like the activity room, basketball field and shop are  completed and ready, and greening area is being provided for the camp area. Till  now, a completely functional and lively community is built in the barren desert.  Despite various difficulties during the construction, all personnel involved in  the construction of the camp area made their utmost efforts, and after several  discussions with the Owner, the construction of the camp area proceeded  smoothly, which will provide significant guarantee for the livelihood of all  site staff to be involved in the construction of the main plant.  

信息来源: 
2022-04-18