The First Batch of Completion Certificates Signed and Issued by NDA Owner of Saudi Arabia

time:2022-04-19 source:

On  Feb. 10, the owner, NDA project department of Saudi Kayan, issued the first  batch of completion certificates to the NDA project of our Company, which marked  that the owner started to approve and receive the completion applications  submitted by NDA project department of SNEI to the owner in  batches.

SNEI’s  EPC project (NDA project in Saudi Arabia) is divided into 286 subsystems in  total and totally 92 systems in terms of completion & delivery. The owner  approved and received 6 subsystems in total this time. Inspection, reception and  approval of other completion applications submitted by SNEI are underway by the  owner item by item.

Produced By CMS 网站群内容管理系统 publishdate:2026-07-27 17:24:01